A and B can do a peice of work in 18 days B and c in 24 days and A and c in 36 days how much time will a Alone take to finish tha work
Respostas
respondido por:
2
Resposta:
15
Explicação passo-a-passo:
A+B=18
B+C=24
A+C=36
From b+c=24 we have that C can be whitten as C=24-B. So,
A+C=36 -> A+(24-B)=36 -> A-B=36-24 ->A-B=12
And,
A+B=18 (1)
A-B=12 (2)
Doing (1) +(2)
2*A=30
A=30/2= 15